How to prepare the subfloor for engineered wood flooring
Installing parquet is an important stage that determines how your floor performs over the years and whether you stay happy with it. Parquet can be glued down or installed as a floating floor on an underlay – we described both methods in detail in one of our articles.
Read also: Installing engineered wood flooring: glue down or floating?
Whichever method you choose, the subfloor must meet certain requirements: it must be flat, dry, strong and clean.
More about preparing a concrete subfloor for parquet installation.
The subfloor must be flat
What does it mean?
The subfloor must be free of cracks and chipped areas. The height difference must not exceed 2 mm over a 2 m length of the surface.
How to check?
Use an ordinary spirit level to measure the deviation from the required level across the whole room.
How to fix it?
An uneven subfloor can be levelled with a filler or with special self-levelling compounds. These materials must bond well to the subfloor and have a strength of at least 15 N/mm2.

The subfloor must be dry
What does it mean?
The permanent moisture content of the subfloor must not exceed 4%.
How to check?
With a special moisture meter. If you do not have one, you can do a simple test with polyethylene film.
Tape a 1×1 m piece of film to the subfloor and leave it for two days. If condensation forms on the underside after two days, the subfloor is not dry enough.
How to fix it?
Switch on the heating and make sure the room is well ventilated. Then wait until the subfloor dries out. If that does not help, the source of moisture must be removed.
The subfloor must be strong
What does it mean?
For installing engineered wood flooring, the compressive strength of the subfloor must be at least 15 N/mm2. If the strength is lower, the subfloor may crack while the floor is in use.
How to check?
With a special instrument – a sclerometer. A strong subfloor also does not crumble when you scratch it with a nail. This is the simplest way to check the strength of the subfloor.
How to fix it?
A subfloor that is not strong enough can be reinforced with special products, or a new subfloor can be built.

What else you need to know and do before installing parquet:
- Parquet is installed after all construction and finishing work involving increased moisture and dirt has been completed.
- At least two weeks before work starts, all climate systems must be tested and switched on.
- Before installation, the parquet must acclimatise to the temperature and humidity of the room where it will be installed. Leave the sealed packs of boards for 4–5 days in a horizontal position.
- While the floor is being installed, keep a suitable room climate: temperature 18–22 °C, relative air humidity 40–65%.
- Before installing the boards, the subfloor must be cleaned of dirt, dust and debris.